Reglamento de Contratación Pública 2026 de Pakistán: lo que deben hacer ya los organismos

A plain-language guide to Pakistan's Public Procurement Rules 2026 (S.R.O. 1658(I)/2026): what changed from the 2004 Rules, what PPRA and the IMF found, and a 12-month checklist for agencies and project teams.

Risalat Consultants International
2 de noviembre de 2026 · 12 min de lectura · Actualizado el 5 de nov de 2026
Reglamento de Contratación Pública 2026 de Pakistán: lo que deben hacer ya los organismos12 min de lectura

In short: Pakistan's Public Procurement Rules 2026 explained: e-PADS, procurement cells, grievance timelines, mis-procurement and a 12-month compliance checklist.

Ideas clave

Pakistan’s Public Procurement Rules 2026, notified by S.R.O. 1658(I)/2026 on 28 September 2026, replace the 2004 Rules for federal procuring agencies. They make e-PADS compulsory for every procurement, require Procurement Cells staffed by PPRA-accredited officers within twelve months, move grievance handling to committees outside the agency and list the material deviations that can lead to a mis-procurement declaration.

  • e-PADS is mandatory. Rule 8 requires all public procurement to be carried out through the E-Pak Acquisition and Disposal System, and PPRA has said this includes direct contracting.
  • Accreditation has a deadline. Rule 10(2) gives officers in a Procurement Cell twelve months to obtain PPRA accreditation.
  • Grievances move outside the agency. Rule 65 sets up committees completely outside the procuring agency, with a ten-day decision period and a 45-day appeal stage.
  • Mis-procurement is defined. Rule 67(4) lists sixteen material deviations, from bypassing e-PADS to not using standard bidding documents.
  • The evidence explains the change. PPRA’s own 2025–26 review found violations in 80.58% of 103 sampled federal procurements.

Introducción

Las reglas de contratación pública de Pakistán de 2026 son la primera reescritura completa de las reglas federales de contratación en más de dos décadas. La División del Gabinete las notificó bajo la sección 26 de la Ordenanza de la PPRA de 2002, a través del S.R.O. 1658(I)/2026 con fecha del 28 de septiembre de 2026, y entraron en vigor de inmediato.

For procuring agencies, project implementation units and suppliers, the questions are practical. What has changed from the 2004 Rules? Which deadlines now apply? What did the Public Procurement Regulatory Authority (PPRA) and the IMF find that led to these changes? And what should an agency do in the next twelve months to stay compliant?

Esta guía resume las disposiciones principales, citando los números de las normas tal como aparecen en el texto del boletín oficial, y establece una lista de comprobación para las agencias y los equipos de proyectos financiados por donantes. Es un resumen en lenguaje sencillo, no asesoramiento legal: los funcionarios siempre deben trabajar a partir del texto notificado y de cualquier regulación o aclaración emitida por la PPRA.

Qué cambian las Reglas de Contratación Pública 2026

Las Reglas de 2026 derogan las Reglas de Contratación Pública de 2004 (Regla 69). Los procedimientos iniciados antes de la entrada en vigor de las nuevas Reglas continúan bajo las Reglas de 2004 (Regla 68), por lo que las agencias mantendrán dos conjuntos de expedientes durante algún tiempo y deben etiquetar cada contratación claramente.

The main shifts are:

  • Digital por defecto: toda la contratación a través de e-PADS (Regla 8), con ofertas abiertas a través del sistema.
  • Unidades de contratación profesionales: una Célula de Contratación en cada organismo bajo el Oficial Principal de Contabilidad o Director (Reglas 9 y 10).
  • Comités más fuertes: miembros acreditados en los comités de evaluación de ofertas, validación de terceros para adquisiciones grandes y miembros externos para las más grandes (Reglas 11 a 13).
  • Independent complaints: grievance redressal committees drawn from outside the agency, with an appeal to PPRA’s Appellate Committee (Rule 65).
  • Consecuencias claras: una lista definida de desviaciones materiales que pueden conducir a una adquisiciones incorrectas (Regla 67(4)).
  • Contract stage duties: third-party performance evaluation for large contracts and inspection rules (Rules 60 and 61).

Rule 5 keeps an important exception: where the Rules conflict with an obligation under an international treaty, an agreement with another state or an arrangement with an international financial institution, that obligation prevails to the extent of the conflict.

e-PADS, unidades de adquisiciones y el plazo de 12 meses

Rule 8 requires procuring agencies to carry out public procurement through e-PADS. In a clarification issued on 30 September 2026, reported by the state news agency APP, PPRA said that this applies to every procurement type, including direct contracting.

Rule 9 makes the Principal Accounting Officer or Head of the procuring agency responsible for establishing a Procurement Cell under Rule 10. Officers in the Cell must be accredited by PPRA; those who are not yet accredited must obtain accreditation within twelve months of the notification establishing the Cell (Rule 10(2)). The Cell prepares quarterly reports on the agency’s procurement for the Principal Accounting Officer or Head (Rule 10(3)(o)).

The same twelve-month allowance appears for bid evaluation committees: Rule 11 requires at least one qualified, experienced and accredited member, and an unaccredited member may be appointed provided accreditation follows within twelve months. PPRA’s draft National Procurement Strategy 2025–28 describes four accreditation levels: Basic, Intermediate, Advance and Expert.

Methods, Thresholds and Framework Agreements

Open competitive bidding is the principal method (Rule 26(1)(a)). Any other method needs written justification (Rule 15(4)). The main value bands in the gazette text are:

  • Below Rs200,000: shopping without quotations (Rule 32(1)(a)).
  • De Rs200,000 a menos de Rs700,000: compra mediante al menos tres cotizaciones, adjudicada al precio más bajo (Regla 32(1)(b)).
  • De Rs700,000 a Rs2 millones: licitación rápida, con un tiempo mínimo de respuesta de cinco días y una declaración de mantenimiento de la oferta (Regla 31).
  • Force account: up to Rs200 million (Rule 32(1)(e)).

La contratación directa se limita a las condiciones de la Regla 32(1)(c), con pedidos repetidos limitados al quince por ciento del contrato original. La Regla 32(1)(f) permite la contratación directa con entidades estatales en casos limitados, con la subcontratación limitada al 40% del trabajo asignado; superar ese límite se trata como una desviación sustancial. La aclaración de la PPRA enfatizó que esta vía es para circunstancias excepcionales y no otorga preferencia a las entidades estatales.

La regla 30 introduce los acuerdos marco: marcos cerrados por hasta un año y marcos abiertos por hasta tres años. Para las agencias que compran los mismos bienes muchas veces al año, esto puede reducir las licitaciones repetidas, pero requiere una planificación cuidadosa y una gestión de contratos.

Publication duties are also clearer. Annual procurement plans go on e-PADS and the PPRA website (Rule 15(2)). Procurements above Rs200,000 are published on e-PADS and the PPRA website, and those above Rs5 million also in at least two national dailies, one English and one Urdu (Rule 18). Minimum response times are ten days for national and twenty days for international competitive bidding (Rule 19).

Evaluation, Validation and Publication of Results

Las reglas escalan la supervisión según el valor. Los comités de evaluación de ofertas gestionan contrataciones de hasta 2 mil millones de rupias (Regla 11). Las contrataciones superiores a 500 millones de rupias y de hasta 2 mil millones de rupias pasan a un comité de validación de terceros cuyos miembros provienen de fuera de la agencia (Regla 12). Por encima de 2 mil millones de rupias, el comité de evaluación debe incluir al menos dos miembros de fuera de la agencia (Regla 13).

Agencies must use the standard bidding documents notified by PPRA (Rule 34(1)). Bid validity extensions are allowed only in exceptional circumstances, with reasons recorded, and may not exceed the original validity period in total (Rule 37(3)). Bid security is capped at 5% for procurements up to Rs250 million and 2% above that (Rule 36).

Los resultados deben publicarse antes de la adjudicación con una breve justificación (regla 48), y los documentos de evaluación y adjudicación deben hacerse públicos en el e-PADS tras la adjudicación (regla 57). Los registros se conservan durante al menos cinco años (regla 56). Tras la adjudicación, los contratos superiores a 500 millones de rupias requieren una evaluación de rendimiento por un tercero (regla 60), y la inspección previa al envío por un tercero se aplica a contrataciones importantes superiores a 1 000 millones de rupias o entregas transfronterizas (regla 61).

Quejas, recursos y errores en las contrataciones bajo la Regla 67

La regla 65 establece el proceso de quejas. Las quejas sobre los documentos de licitación deben presentarse dos días antes de la fecha límite de presentación; las quejas posteriores a la presentación de ofertas, dentro de los siete días posteriores al informe de evaluación técnica o cinco días posteriores al informe de evaluación final. El comité de resolución de quejas, constituido completamente fuera de la agencia contratante, decide en un plazo de diez días. Se puede presentar un recurso ante el Comité de Apelaciones de la PPRA dentro de los diez días posteriores a dicha decisión, sujeto a una tarifa prescrita, y se resuelve en un plazo de 45 días; esa decisión es definitiva.

La Regla 67(4) enumera dieciséis desviaciones materiales. Estas incluyen prácticas corruptas, colusorias, coercitivas, fraudulentas u obstructivas; eludir el sistema e-PADS; contratar sin la Célula de Adquisiciones o los comités requeridos; especificaciones hechas a medida; incumplimiento de las normas de publicación o plazos de respuesta; no utilizar documentos estándar de licitación; evaluar según criterios no establecidos de antemano; condiciones discriminatorias; no publicar los documentos de evaluación o adjudicación; y no contar con un comité de inspección de bienes. Las desviaciones no materiales pueden ser condonadas, pero cuando la contratación supera los 250 millones de rupias, el asunto pasa a la Autoridad o a un comité constituido por esta (Regla 67(6)).

Rule 25 sets blacklisting periods of up to ten years for corrupt or fraudulent practices, up to five years for false or misleading information and six months for non-performance, consistently abnormally low bids or failing to honour a bid-securing declaration, with a review petition to PPRA within thirty days.

What PPRA’s Own 2026 Reports Found

In September 2026 PPRA published two federal reports for 2025–26. They describe procurement under the rules then in force and show where the new Rules are aimed.

The compliance and violations report reviewed 103 open competitive procurements from 101 agencies. It rated 19.42% compliant, 47.57% partially compliant and 33.01% non-compliant; 80.58% had at least one violation. Among the procurements with violations, 40.96% had not adopted national standard bidding documents, 36.14% were awarded after bid validity expired without a recorded extension, 9.64% had not published evaluation and award documents on e-PADS and 8.43% had not uploaded evaluation reports before award. Contract agreements could not be confirmed for 34.95% of the sample.

The monitoring report, based on e-PADS 1.0 data, counted 62,652 planned procurements and 51,989 awarded records worth PKR 409.72 billion. Open competitive bidding made up 9.60% of records but 98.44% of value. It took an average of 101.48 days from publication to award (median 94.08), attracted an average of 4.52 bidders (median 3), and 12.25% of open bidding records received a single bid. The report itself notes some data inconsistencies that will be revisited after e-PADS 2.0 integration, so these figures are best read as indicative.

El borrador de la Estrategia Nacional de Adquisiciones añade la visión de sistema: solo los módulos de presentación de ofertas están disponibles en e-PADS, las garantías aún se recaudan físicamente, las adquisiciones financiadas por bancos multilaterales a menudo se ejecutan de forma aislada y la mayoría de las agencias carecen de unidades de adquisiciones especializadas. Planifica módulos de gestión electrónica de contratos y de bancos multilaterales.

Lo que solicitó el diagnóstico de gobernanza y corrupción del FMI

El informe de asistencia técnica del FMI, Diagnóstico de Gobernanza y Corrupción de Pakistán, concluyó que la contratación pública seguía fragmentada y privilegiaba a las partes estatales. Señaló que algunas entidades, como NHA, CDA y WAPDA, continuaban utilizando sus propios sistemas, que no existía una base de datos de contratación estructurada y legible por máquina, que las denuncias federales tardaban de dos a seis meses en resolverse, que las decisiones sobre las denuncias no se publicaban y que una tasa de apelación significativa reducía la eficacia.

Its recommendations for PPRA included removing preferences for state-owned firms and charitable organisations, quarterly monitoring reports for development and non-development spending, mandatory use of e-PADS (the executive summary says within 12 months, the recommendations table within 18 months), mandatory certification of procurement professionals with dedicated procurement cells, and standards for resolving complaints with public reporting on grievances.

Varios de estos elementos aparecen ahora en las Normas: el mandato del e-PADS, las unidades de contratación con oficiales acreditados, los comités externos de reclamaciones y la reducción de la contratación directa en empresas estatales. La publicación de las decisiones sobre reclamaciones no es un requisito explícito en el texto de la gaceta, y las Normas todavía contemplan una tarifa de apelación, por lo que estas siguen siendo áreas a tener en cuenta.

Donor-Financed Projects: World Bank, ADB and Rule 5

Los equipos de proyecto deben determinar qué reglas se aplican a cada contrato. Según la Regla 5, las obligaciones bajo acuerdos con instituciones financieras internacionales prevalecen en caso de conflicto con las Reglas. Para la financiación de proyectos de inversión del Banco Mundial, las adquisiciones siguen las Regulaciones de Adquisiciones para Prestatarios de IPF (séptima edición, septiembre de 2025); los proyectos financiados por el ADB siguen el marco de adquisiciones del ADB, incluida su Instrucción técnica sobre adquisiciones administradas por el prestatario.

Where financing agreements allow national procurement procedures, the 2026 Rules and e-PADS become directly relevant to donor projects. The World Bank’s Public Resources for Inclusive Development operations are an example. The federal phase (P509827, US$600 million) cites delays and leakages in procurement and plans to strengthen procurement, including through expansion of e-procurement; its US$30 million investment component finances technical assistance, consultancies, IT systems and borrower capacity strengthening. The Sindh phase (P511459, US$200 million) notes that the province is adopting e-procurement and an asset disposal system, with a US$30 million investment component that includes capacity building.

Las normas provinciales también importan. Punjab anunció un despliegue de contratación electrónica en toda la provincia a partir del 1 de julio de 2026, mientras que en Sindh, Transparency International Pakistan, según informó The News, objetó las exenciones que permitieron a dos departamentos continuar con la licitación manual.

Una lista de verificación de 12 meses para organismos contratantes y equipos de proyectos

La siguiente tabla agrupa las acciones principales. El momento oportuno depende de las fechas de notificación de cada agencia y de cualquier regulación adicional de la PPRA.

AcciónRuleCuándo
Notify the Procurement Cell and assign officersReglas 9, 10Ahora
Plan de acreditación para oficiales de células y miembros del comité de evaluaciónReglas 10(2), 11En el plazo de 12 meses
Run every procurement, including direct contracting, on e-PADSRegla 8Ahora
Publicar el plan anual de adquisiciones en e-PADS y en el sitio web de la PPRARegla 15(2)Each year
Utilizar los documentos estándar de licitación de la PPRAReglas 34(1), 67(4)Cada contratación
Track bid validity and record any extension in writingRegla 37(3)Cada contratación
Publish results before award and documents after awardReglas 48, 57Cada contratación
Arrange external grievance committees and third-party validationReglas 12, 65Before the first case
Planificar la evaluación de desempeño y la inspección de contratos grandesReglas 60, 61Desde la firma del contrato
Informe trimestral al Oficial Principal de Contabilidad o DirectorRule 10(3)(o)Cada trimestre
Registrar qué reglas se aplican a los contratos financiados por donantesRegla 5Ahora

Las agencias que deseen un punto de partida estructurado pueden comparar su práctica actual con esta lista mediante una autoevaluación y luego convertir las deficiencias en un plan con responsables y fechas.

Preguntas críticas que deberían plantearse los responsables gubernamentales y de proyectos

¿Sabemos cuáles de nuestras adquisiciones se rigen por las Reglas de 2004 y cuáles por las Reglas de 2026?

Rule 68 keeps earlier proceedings under the 2004 Rules. A simple register that tags each file avoids applying the wrong timelines or documents.

How many of our procurement staff and committee members are accredited today?

El plazo de doce meses establecido en las reglas 10(2) y 11 es corto para las grandes agencias. Una lista de nombres, estado actual y fechas de capacitación previstas es el primer paso.

Are we still running any procurement outside e-PADS?

Bypassing e-PADS is a material deviation under Rule 67(4). Agencies should identify every exception, including small purchases and direct contracts, and move them onto the system.

¿Podemos demostrar que las evaluaciones terminan dentro de la validez de la oferta?

PPRA’s 2025–26 review found that 36.14% of procurements with violations were awarded after validity expired. A timeline tracker and early decisions on extensions under Rule 37(3) reduce this risk.

¿Quiénes formarán parte de nuestros comités de resolución de reclamaciones y cómo cumpliremos con el plazo de diez días?

La Regla 65 exige miembros de fuera del organismo. Los organismos deben acordar los arreglos con antelación en lugar de buscar miembros cuando llega una queja.

¿Cómo gestionamos los contratos mientras e-PADS no tiene un módulo de contratos?

El borrador de la estrategia planifica un módulo de gestión de contratos electrónicos. Hasta entonces, un registro de contratos, informes de rendimiento y acuerdos firmados cargados con los documentos de adjudicación ayudan a cumplir con las reglas 57 y 60.

Cómo puede ayudar Risalat

Risalat se asocia con agencias contratantes y equipos de proyectos para poner en práctica las nuevas normas de contratación. Nuestra capacitación sobre el cumplimiento de las normas de contratación pública de 2026 y e-PADS en Dubái abarca la planificación, los métodos, la evaluación, las reclamaciones, las contrataciones irregulares y la gestión de contratos utilizando los propios archivos de los participantes, y se puede impartir de forma interna. Las agencias también pueden realizar nuestra evaluación diagnóstica de madurez en contratación gratuita para evaluar su función de contratación antes de planificar el próximo año.


Preguntas frecuentes

¿Cuándo entraron en vigor las normas de contratación pública de Pakistán de 2026?

They were notified by S.R.O. 1658(I)/2026 on 28 September 2026 and came into force at once. Procurements started earlier continue under the 2004 Rules (Rule 68).

¿Es obligatorio el e-PADS según las Reglas de 2026?

Yes. Rule 8 requires procuring agencies to carry out public procurement through e-PADS, and PPRA has clarified that this includes direct contracting. Bypassing e-PADS is a material deviation under Rule 67(4).

¿Cuánto tiempo tienen los oficiales de adquisiciones para obtener la acreditación de la PPRA?

La Regla 10(2) concede a los funcionarios no acreditados en una Célula de Adquisiciones doce meses a partir de la notificación de creación de la Célula; la Regla 11 concede el mismo plazo a los miembros no acreditados del comité de evaluación.

¿Con qué rapidez se deben decidir las quejas sobre adquisiciones?

Bajo la Regla 65, el comité de resolución de quejas decide en un plazo de diez días. Un recurso ante el Comité de Apelación de la PPRA debe presentarse en un plazo de diez días y se resuelve en 45 días.


Fuentes

  1. Public Procurement Rules, 2026 (S.R.O. 1658(I)/2026), Gazette of Pakistan
  2. PPRA: Informe de análisis de cumplimiento y violaciones de contratación pública año fiscal 2025-26
  3. PPRA: Federal Public Procurement Monitoring Report FY2025-26
  4. PPRA: Draft National Procurement Strategy 2025-28
  5. IMF Technical Assistance Report: Pakistan Governance and Corruption Diagnostic
  6. APP: Aclaración de la PPRA sobre las Reglas de Contratación Pública 2026 (30 de septiembre de 2026)
  7. World Bank PID: PRID MPA Phase 1 Federal (P509827)
  8. World Bank PID: PRID MPA Phase 1 Sindh (P511459)
  9. Marco de Adquisiciones del Banco Mundial
  10. Marco de adquisiciones del ADB
  11. PITB: Conferencia de contratación electrónica de Punyab (junio de 2026)
  12. La noticia: Instan al ministro principal de Sindh a revocar la exención del EPADS

Ver

Compartir con su equipo

Know people who should read this? Become an Ambassador or write with Risalat.

Risalat Consultants International

Socios para el éxito de los proyectos desde 2011: diagnósticos, asesoría y aprendizaje aplicado para ministerios, organismos públicos y equipos de proyecto.

¿Necesita ayuda para llevar esto a la práctica?

Empiece con un diagnóstico gratuito de 10 minutos o hable con nuestros expertos.