Home › Free tools › Procurement and Contract Delay Analyser
Enter each package's planned and actual dates for four stages: bidding document issued, bids opened, evaluation and award decision, and contract signed. Or import a CSV or Excel export of your procurement plan. The analyser compares actual with planned dates, checks the bid preparation and evaluation periods against the World Bank Procurement Regulations (current edition, September 2025) and your bid validity, finds the bottleneck stage and suggests recovery actions. Everything runs in your browser.
Need a verified result? Ask for an independent assessment by Risalat.
Upcoming programmes whose content matches the areas this tool measures. Your results show which fit your weakest areas.
Nothing here for your exact need? Ask for an in-house programme built around your gaps, or browse all programmes.
CSV and Excel (.xlsx) files with one package per row and columns for planned and actual dates. The analyser recognises common column names; you can correct anything after the import.
The minimum bid preparation period for open international procurement (30 business days under the World Bank Procurement Regulations), evaluation time against your bid validity period, the standstill period before signature, and long gaps between stages.
No. The file is read in your browser and nothing is uploaded unless you save your work to a free account.
Sources checked: October 2026. We check the official sources every month.
This analyser compares dates you enter with your plan and with a few published rules. It is not an official procurement review: always follow your financing agreement, the applicable procurement regulations and your procurement plan as agreed with the financier.
Is the delay a training problem at all? Find the real cause before you train.
Essential cookies keep this site secure. With your permission we also use analytics and advertising cookies. Cookie policy
Google Analytics counts visits: in the EU, the UK and Switzerland only after you accept, elsewhere unless you reject it. You can change your choice at any time from “Cookie settings” at the bottom of every page.
Most likely fit
Also worth a look
Less indicated by this result
Bid document issued
Bids opened
Evaluation and award decision
Contract signed
Bid validity
Bid document issued late in {n} package(s): preparing specifications, estimates and documents is a skill the team can build.
Bid document issued late in {n} package(s): check internal clearance and prior review timing as well.
Bid opening moved in {n} package(s): check how addenda, clarifications and deadline extensions are approved.
Evaluation and award decision late in {n} package(s): check committee appointment, report approval and no-objection steps.
Evaluation and award decision late in {n} package(s): evaluation reports may need practice with real cases.
Contract signature late in {n} package(s): check signature approvals, securities and other dependencies.
Long gaps between stages in {n} package(s): look for steps that wait on another unit.
{x} late in {n} packages: a recurring pattern often points to a practice gap.
Evaluation outlasted the bid validity in {n} package(s): confirm extensions and their effect on bids before any award.
More than half of the bid validity used in {n} package(s): plan extensions before the deadline.
Bid preparation period below the minimum in {n} package(s): an independent check before award is advisable.
Signature soon after the award decision in {n} package(s): confirm the standstill period was respected.
{x}: {n}%
Matched from the type of tool, as this result has no scores by area.
Nothing in this result points here.
No clear gap in this result. If problems persist, a short conversation helps locate them.
Overall result: {n}%
Lowest areas: {x}
{n} package(s) analysed, {x} behind plan
{x}: late in {n} package(s)
Bid validity and rule flags: {n}
Score: {x}
Result: {x}
Please complete the highlighted fields.
Connection problem. Please try again.
Sending…
A work email helps us confirm your institution and reply faster. A personal address is accepted.
See your result ↓
Back to questions ↑
A late stage or a low score shows where time or quality is being lost. It does not, on its own, show why. The cards below suggest which kind of support is most likely to fit, so a first conversation starts in the right place.
The team may need applied learning or coaching: practical work on its own files, so people can apply the rules and methods with confidence.
The institution may need to review its steps, approvals and dependencies: who signs, in what order, how long each step takes and what waits on what.
Dates, deadlines or validity periods are under pressure. A verified independent assessment is advisable before acting, so decisions rest on confirmed facts.
Screening aid, not a verified assessment. The matching uses your answers and a few fixed rules. Our specialists confirm the cause with you before recommending anything.
A confirmation is on its way to your inbox.
The Risalat Brief: one short report a week on a real delivery problem in procurement, safeguards, M&E or public finance, its causes and what works. No adverts; unsubscribe any time.