Inicio › Herramientas gratuitas › Evaluación de la madurez de la PMO de megaproyectos
Para PMO y equipos del propietario de gigaproyectos, grandes programas de infraestructura y proyectos con varios contratistas financiados por donantes. Responda a 24 preguntas sobre cómo se gobierna y controla el programa. Obtendrá una puntuación de madurez en ocho áreas, las carencias que con más frecuencia provocan sobrecostes, recomendaciones para su nivel en cada área y un plan de 90 días.
Finish to see how you compare with other professionals, then challenge a colleague to beat your score.
¿Necesita un resultado verificado? Solicite una evaluación independiente a Risalat.
Próximos programas cuyo contenido coincide con las áreas que mide esta herramienta. Sus resultados muestran cuáles se ajustan a sus áreas más débiles.
¿No encuentra nada para su necesidad concreta? Solicite un programa interno diseñado en torno a sus brechas o explore todos los programas.
No. Sirve para cualquier programa grande o con varios contratistas, incluidos los grandes proyectos financiados por donantes con varios contratos de obras. Las preguntas tratan sobre lo bien controlado que está el programa, sea cual sea su tamaño.
Sí. Con una cuenta gratuita puede invitar a colegas de planificación, costes, riesgos, contratos y del lado del cliente, y ver en qué difieren sus opiniones.
No. Es una autoevaluación rápida que muestra dónde centrarse. Una evaluación formal de madurez o una revisión independiente de puerta de fase profundiza más y examina evidencias.
Fuentes verificadas: noviembre de 2026. Revisamos las fuentes oficiales cada mes.
Una herramienta de orientación, no una evaluación formal, una auditoría ni un dictamen jurídico. Sus contratos, las políticas del financiador y la legislación nacional prevalecen siempre.
We use essential cookies to run this website securely. With your permission we also use cookies to remember your choices and to measure our advertising. To understand how the site is used we count visits with Google Analytics: in the EU, the UK and Switzerland only after you accept, elsewhere unless you reject it. You can change your choice at any time from “Cookie settings” at the bottom of every page. Privacy and cookie policy
Most likely fit
Also worth a look
Less indicated by this result
Bid document issued
Bids opened
Evaluation and award decision
Contract signed
Bid validity
Bid document issued late in {n} package(s): preparing specifications, estimates and documents is a skill the team can build.
Bid document issued late in {n} package(s): check internal clearance and prior review timing as well.
Bid opening moved in {n} package(s): check how addenda, clarifications and deadline extensions are approved.
Evaluation and award decision late in {n} package(s): check committee appointment, report approval and no-objection steps.
Evaluation and award decision late in {n} package(s): evaluation reports may need practice with real cases.
Contract signature late in {n} package(s): check signature approvals, securities and other dependencies.
Long gaps between stages in {n} package(s): look for steps that wait on another unit.
{x} late in {n} packages: a recurring pattern often points to a practice gap.
Evaluation outlasted the bid validity in {n} package(s): confirm extensions and their effect on bids before any award.
More than half of the bid validity used in {n} package(s): plan extensions before the deadline.
Bid preparation period below the minimum in {n} package(s): an independent check before award is advisable.
Signature soon after the award decision in {n} package(s): confirm the standstill period was respected.
{x}: {n}%
Matched from the type of tool, as this result has no scores by area.
Nothing in this result points here.
No clear gap in this result. If problems persist, a short conversation helps locate them.
Overall result: {n}%
Lowest areas: {x}
{n} package(s) analysed, {x} behind plan
{x}: late in {n} package(s)
Bid validity and rule flags: {n}
Score: {x}
Result: {x}
Please complete the highlighted fields.
Connection problem. Please try again.
Sending…
A work email helps us confirm your institution and reply faster. A personal address is accepted.
See your result ↓
Back to questions ↑
A late stage or a low score shows where time or quality is being lost. It does not, on its own, show why. The cards below suggest which kind of support is most likely to fit, so a first conversation starts in the right place.
The team may need applied learning or coaching: practical work on its own files, so people can apply the rules and methods with confidence.
The institution may need to review its steps, approvals and dependencies: who signs, in what order, how long each step takes and what waits on what.
Dates, deadlines or validity periods are under pressure. A verified independent assessment is advisable before acting, so decisions rest on confirmed facts.
Screening aid, not a verified assessment. The matching uses your answers and a few fixed rules. Our specialists confirm the cause with you before recommending anything.