In short: Road maintenance in Zambia: what audits reveal about arrears, interest and variations, the OPRC handover, TRACER and road concessions, and next steps.
Ideas clave
Road maintenance in Zambia depends on three things working together: steady money, good contracts and timely payment. Recent audits and financed projects show where the system is under pressure and what can be done about it.
- Arrears. A special audit reported that the Road Development Agency owed contractors and consultants about K9.89 billion at the end of 2022 and accrued K1.3 billion in interest for late payment.
- Variations. Fourteen contracts valued at K4.53 billion grew to K6.65 billion, adding K2.13 billion.
- Handover. The World Bank-financed Improved Rural Connectivity Project, which used performance-based contracts for feeder roads, reached its closing date at the end of 2025.
- New obligations. TRACER, a US$270 million World Bank grant, and 11 reported road concessions add long-term maintenance and contract commitments.
- Next step. Linking maintenance plans, contract commitments and cash forecasts is the most practical way to protect road budgets.
Introducción
Zambia has invested heavily in roads, from feeder roads in rural districts to dual carriageways and regional corridors. The harder task is keeping those roads in good condition year after year. Road maintenance in Zambia is financed mainly through the Road Fund and tolling, managed by the National Road Fund Agency (NRFA), and delivered through contracts let by the Road Development Agency (RDA) and local road authorities.
Audit reports, World Bank project documents and recent agency statements give a useful picture of where the system works and where money is lost before it reaches the road. This article brings them together and sets out practical steps for agencies, the Ministry of Finance and National Planning and project teams. It uses only published sources.
How Road Maintenance in Zambia Is Financed
The NRFA mobilises and manages road sector funds, while the RDA is responsible for constructing and maintaining public roads and oversees projects such as the National Road Tolling Programme. A UNDP road safety investment case notes, citing the NRFA’s 2020 annual report, that the Road Fund received ZMK 8.87 billion in 2020.
Los ingresos son solo una parte de la imagen. Una versión simplificada del informe del Auditor General de 2023, publicada con Transparency International Zambia, señala que el NRFA recaudó en exceso 657 millones de K, pero permitió que los camiones sobrecargados pasaran sin multas. La sobrecarga acelera el daño al pavimento, por lo que la aplicación de la ley es en sí misma un problema de financiamiento del mantenimiento.
Parliament has also considered an Auditor General report on the utilisation of the Road Fund for road maintenance over 2020–2024, which shows how closely the use of maintenance money is now being followed.
Arrears and Interest: What the RDA Special Audit Found
The special audit of the RDA for 2017–2022, issued by the Acting Auditor General, is the clearest evidence of how late payment drains road budgets. It reported that:
- the RDA contracted 24 companies for 24 projects with contract sums of about K9.80 billion between 2017 and 2022;
- at 31 December 2022, the RDA owed contractors and consultants about K9.89 billion;
- failure to settle bills on time led to K1.3 billion in interest charges;
- 14 contratos valorados originalmente en unos 4,530 millones de K se modificaron a unos 6,650 millones de K, lo que supone un aumento de 2,130 millones de K;
- advance payments of about K90.95 million had not been recovered from three contractors.
La auditoría recomendó que la RDA priorizara y presupuestara los proyectos en consonancia con las aprobaciones del Ministerio de Finanzas y Planificación Nacional, cumpliera con las normativas de finanzas y adquisiciones, y satisficiera los requisitos de garantía de calidad antes del pago.
| Finding (RDA special audit, 2017–2022) | Amount |
|---|---|
| Owed to contractors and consultants at end-2022 | alrededor de K9,89 mil millones |
| Intereses por pago atrasado | about K1.3 billion |
| Added through variations on 14 contracts | alrededor de 2.130 millones de K2 |
| Unrecovered advance payments (three contractors) | about K90.95 million |
How arrears build up
Arrears rarely come from a single decision. They build up when several contracts are signed in the same budget year on the assumption that funding will follow, when certificates wait for approval at several levels, and when exchange rate movements or variations raise the amount due. Each step looks reasonable on its own; together they produce a stock of unpaid bills that attracts interest and weakens contractors, who may then slow down or claim for delay.
Por qué el interés es el costo más evitable
Los intereses por demora no compran ningún camino. Surgen cuando los contratos se firman por encima del efectivo disponible o cuando los certificados se acumulan en las colas de aprobación. Alinear los compromisos con los techos presupuestarios a mediano plazo y realizar un seguimiento de los certificados hasta el pago se cuentan entre las reformas de menor costo disponibles.
Contract Management Beyond the RDA
The same themes appear elsewhere in government. The Auditor General’s report for 2024 recorded 33 critical findings unresolved at the end of September 2025 and called for tighter procurement oversight and improved contract management. It noted, for example, that the Ministry of Water Development and Sanitation terminated contracts worth K48.4 million with K15.4 million in advance payments unrecovered. The 2024 parastatal report found that the Rural Electrification Authority had K22.5 million exposed through unrecovered advances, missing guarantees and uncharged liquidated damages.
For road agencies, these findings point to three routine controls: a register of every advance payment and the guarantee that secures it, with expiry dates; a clear rule for charging liquidated damages; and a variation procedure with approval thresholds linked to the budget.
After the World Bank OPRCs: Who Keeps Feeder Roads Open?
In 2017 the World Bank approved a US$200 million credit for the Improved Rural Connectivity Project, noting that only 17% of Zambia’s rural population lived within 2 km of a good road. The project used output and performance-based road contracts (OPRC), in which contractors are paid for keeping roads at agreed service levels rather than for quantities of work.
The project’s closing date was 31 December 2025. Its results framework includes an indicator on whether government-funded road maintenance contracts exist for continued upkeep after the Bank-supported OPRC contracts end. That is the practical test now. Without a funded maintenance plan, gains on feeder roads can be lost within a few rainy seasons.
What a sound handover looks like
- Una lista de cada sección de carretera que salió de un contrato OPRC, con su estado en el momento de la entrega
- A costed annual maintenance need for those sections, included in the Road Fund allocation
- A contracting model, performance-based or routine, with clear service levels
- Assigned responsibilities between the RDA and local road authorities
New Commitments: TRACER and Road Concessions
En febrero de 2024, el Banco Mundial aprobó una subvención de 270 millones de dólares estadounidenses para el proyecto TRACER, que rehabilitará el tramo Serenje-Mpika del corredor de Dar es Salaam, construirá un puesto fronterizo de ventanilla única en Nakonde y convertirá el corredor en un corredor INTELIGENTE. Los documentos del proyecto incluyen apoyo a la gestión regional de corredores y al desarrollo de capacidades institucionales en entidades gubernamentales.
The RDA has also reported 11 PPP concession agreements to upgrade and maintain over 1,002 km of roads, including the Lusaka–Ndola dual carriageway. An AfDB-supported pipeline study reviews Zambia’s PPP framework under the 2023 PPP Act and includes building the capacity of local practitioners to monitor and develop the pipeline. Concessions shift construction finance to private partners, but they create long-term monitoring duties and possible contingent liabilities that need clear reporting.
Lessons From Kenya’s Road Levy
Kenya offers a useful comparison. It raised its Road Maintenance Levy from Sh18 to Sh25 per litre in July 2024, and the Kenya Roads Board distributes it to national, urban, rural and county road authorities. Kenya Roads Board data shows a public network of 239,122 km in 2024 and an annual maintenance financing gap of Sh63 billion. In the year to June 2025, roads repaired fell 28% to 35,965 km after part of the levy was redirected. The lesson is that a dedicated fund helps, but only if its allocation rules are protected and transparent.
Una agenda práctica para 2027
None of the steps below needs new legislation or large new budgets. Most are management routines that road agencies, road funds and the finance ministry can agree and start within a year. Together they address the main sources of loss identified in the audits: commitments made without matching cash, payments delayed in approval queues, variations approved without budget checks and securities that are not tracked.
| Acción | Lead | What it prevents |
|---|---|---|
| Annual maintenance needs estimate from condition data, linked to Road Fund allocations | RDA, NRFA, local road authorities | Deterioro de carreteras rehabilitadas |
| Commitment check against medium-term budget ceilings before signing contracts | RDA, Ministry of Finance and National Planning | New arrears and interest |
| Certificate-to-payment tracking with target timelines | RDA, NRFA | Interest on late payment |
| Single register of advance payments, guarantees and expiry dates | RDA contracts unit | Unrecovered advances |
| Variation approval thresholds with budget confirmation | Gestión y junta directiva de la RDA | Uncontrolled growth in contract values |
| Plan de mantenimiento financiado para cada antigua sección OPRC | RDA, local road authorities | Loss of feeder road gains |
| Monitoring plan and fiscal risk reporting for each concession | RDA, PPP institutions, Ministry of Finance | Unplanned contingent liabilities |
| Audit recommendation tracker reported quarterly | All road sector bodies | Repeat findings |
Protecting the road from overloading
Maintenance financing is also about reducing damage in the first place. Heavy vehicles that exceed axle load limits shorten pavement life. Consistent weighbridge enforcement, accurate fine collection and data sharing between weighbridge operators and the road fund reduce the maintenance bill and support the case for protecting road fund revenue. Corridor projects that include new weighbridge facilities, as TRACER does at Mpika, are a good place to set these routines from the start.
Building skills across institutions
La mayoría de estas rutinas se sitúan entre instituciones: la agencia vial, el fondo vial, las autoridades viales locales y el ministerio de finanzas. La capacitación conjunta y las herramientas compartidas, como un formato común de registro de contratos y un método acordado de necesidades de mantenimiento, ayudan a los equipos a trabajar con las mismas cifras y a reducir los retrasos que se producen en cada traspaso.
Preguntas críticas que deberían plantearse los responsables gubernamentales y de proyectos
Do our contract commitments match the cash we expect?
Compare signed contract values and expected certificates with the medium-term budget for each year. Any gap will become arrears and interest.
¿Qué carreteras abandonaron los contratos de mantenimiento financiados por donantes y quién las mantiene ahora?
Every former OPRC section should have a named maintenance arrangement and budget line for 2027.
Can we see every advance payment and guarantee in one place?
Un registro único con fechas de vencimiento previene pagos contra garantías vencidas y anticipos no recuperados.
How are variations approved?
Set thresholds that require budget confirmation before a variation is signed, and record the reason for each one.
How will we monitor concessions for 20 years or more?
Cada concesión necesita un plan de monitoreo que cubra los estándares de desempeño, los ingresos por peajes, las obligaciones de mantenimiento, la devolución y los compromisos fiscales.
Are audit recommendations closed with evidence?
Track each finding with an owner, action, date and evidence, and report progress to the board and Parliament.
Cómo puede ayudar Risalat
Risalat Consultants International partners with road agencies, road funds and finance ministries on maintenance planning, contract management and PPP oversight. Our Road Maintenance Financing & Contract Oversight Training in Nairobi works through these issues with Zambian and regional cases, and can be delivered in-house. Teams can also review their procurement systems with our free procurement maturity diagnostic.
Preguntas frecuentes
¿Quién financia el mantenimiento vial en Zambia?
Mainly the Road Fund and tolling, managed by the National Road Fund Agency, with works delivered by the Road Development Agency and local road authorities.
What did the RDA special audit find?
About K9.89 billion owed to contractors and consultants at end-2022, K1.3 billion in interest for late payment and K2.13 billion added through variations on 14 contracts.
¿Qué es un contrato OPRC?
An output and performance-based road contract pays the contractor for keeping a road at agreed service levels rather than for quantities of work; Zambia's World Bank-financed IRCP used this model.
How many road concessions does Zambia have?
The RDA has reported 11 PPP concession agreements to upgrade and maintain over 1,002 km of roads.
Fuentes
- Zambia Monitor, special audit of the Road Development Agency 2017–2022
- Zambia Monitor, auditoría especial de la RDA (montos de contratos)
- Zambia Monitor, Auditor General's 2024 report
- Zambia Monitor, Auditor General's 2024 parastatal report
- Transparency International Zambia, simplified Auditor General report 2023
- UNDP, Zambia road safety investment case
- World Bank press release, IRCP approval, May 2017
- World Bank project page, IRCP (P159330)
- World Bank press release, TRACER, February 2024
- TRACER project information document (P180801)
- Zambia Monitor, RDA concession agreements
- Aninver, PPP project pipeline development in Zambia (AfDB)
- National Assembly of Zambia, committee report on Road Fund utilisation 2020–2024
- Business Daily, Kenya road maintenance levy
- Business Daily, Kenya road maintenance drops to six-year low
Ver
- Marco y Regulaciones de Adquisiciones para Proyectos Banco Mundial
- World Bank: Transport Banco Mundial
Know people who should read this? Become an Ambassador or write with Risalat.
Socios para el éxito de los proyectos desde 2011: diagnósticos, asesoría y aprendizaje aplicado para ministerios, organismos públicos y equipos de proyecto.
¿Necesita ayuda para llevar esto a la práctica?
Empiece con un diagnóstico gratuito de 10 minutos o hable con nuestros expertos.