In short: Road maintenance in Zambia: what audits reveal about arrears, interest and variations, the OPRC handover, TRACER and road concessions, and next steps.
要点总结
Road maintenance in Zambia depends on three things working together: steady money, good contracts and timely payment. Recent audits and financed projects show where the system is under pressure and what can be done about it.
- Arrears. A special audit reported that the Road Development Agency owed contractors and consultants about K9.89 billion at the end of 2022 and accrued K1.3 billion in interest for late payment.
- Variations. Fourteen contracts valued at K4.53 billion grew to K6.65 billion, adding K2.13 billion.
- Handover. The World Bank-financed Improved Rural Connectivity Project, which used performance-based contracts for feeder roads, reached its closing date at the end of 2025.
- New obligations. TRACER, a US$270 million World Bank grant, and 11 reported road concessions add long-term maintenance and contract commitments.
- Next step. Linking maintenance plans, contract commitments and cash forecasts is the most practical way to protect road budgets.
引言
Zambia has invested heavily in roads, from feeder roads in rural districts to dual carriageways and regional corridors. The harder task is keeping those roads in good condition year after year. Road maintenance in Zambia is financed mainly through the Road Fund and tolling, managed by the National Road Fund Agency (NRFA), and delivered through contracts let by the Road Development Agency (RDA) and local road authorities.
Audit reports, World Bank project documents and recent agency statements give a useful picture of where the system works and where money is lost before it reaches the road. This article brings them together and sets out practical steps for agencies, the Ministry of Finance and National Planning and project teams. It uses only published sources.
How Road Maintenance in Zambia Is Financed
The NRFA mobilises and manages road sector funds, while the RDA is responsible for constructing and maintaining public roads and oversees projects such as the National Road Tolling Programme. A UNDP road safety investment case notes, citing the NRFA’s 2020 annual report, that the Road Fund received ZMK 8.87 billion in 2020.
收入只是问题的一个方面。2023 年总审计长报告的简化版本与国际透明组织赞比亚分会联合发布,指出 NRFA 超收了 6.57 亿克瓦查,却允许超载卡车无罚通过。超载会加速路面损坏,因此执法本身就是一个维护融资问题。
Parliament has also considered an Auditor General report on the utilisation of the Road Fund for road maintenance over 2020–2024, which shows how closely the use of maintenance money is now being followed.
Arrears and Interest: What the RDA Special Audit Found
The special audit of the RDA for 2017–2022, issued by the Acting Auditor General, is the clearest evidence of how late payment drains road budgets. It reported that:
- the RDA contracted 24 companies for 24 projects with contract sums of about K9.80 billion between 2017 and 2022;
- at 31 December 2022, the RDA owed contractors and consultants about K9.89 billion;
- failure to settle bills on time led to K1.3 billion in interest charges;
- 原本估值约 45.3 亿克瓦查的 14 个合同变更为约 66.5 亿克瓦查,增加了 21.3 亿克瓦查;
- advance payments of about K90.95 million had not been recovered from three contractors.
审计建议,RDA应根据财政部和国家规划部的批准优先安排项目并编制预算,遵守财务和采购法规,并在付款前满足质量保证要求。
| Finding (RDA special audit, 2017–2022) | Amount |
|---|---|
| Owed to contractors and consultants at end-2022 | 约98.9亿基纳 |
| 逾期付款利息 | about K1.3 billion |
| Added through variations on 14 contracts | 约21.3亿基纳 |
| Unrecovered advance payments (three contractors) | about K90.95 million |
How arrears build up
Arrears rarely come from a single decision. They build up when several contracts are signed in the same budget year on the assumption that funding will follow, when certificates wait for approval at several levels, and when exchange rate movements or variations raise the amount due. Each step looks reasonable on its own; together they produce a stock of unpaid bills that attracts interest and weakens contractors, who may then slow down or claim for delay.
为什么利息是可以最大程度避免的成本
迟付款的利息修不出道路。这种情况产生于签约超出现金预算,或者审批环节积压了结算凭证。将承诺与中期预算上限相匹配,以及追踪付款凭证,是成本最低的改革举措之一。
Contract Management Beyond the RDA
The same themes appear elsewhere in government. The Auditor General’s report for 2024 recorded 33 critical findings unresolved at the end of September 2025 and called for tighter procurement oversight and improved contract management. It noted, for example, that the Ministry of Water Development and Sanitation terminated contracts worth K48.4 million with K15.4 million in advance payments unrecovered. The 2024 parastatal report found that the Rural Electrification Authority had K22.5 million exposed through unrecovered advances, missing guarantees and uncharged liquidated damages.
For road agencies, these findings point to three routine controls: a register of every advance payment and the guarantee that secures it, with expiry dates; a clear rule for charging liquidated damages; and a variation procedure with approval thresholds linked to the budget.
After the World Bank OPRCs: Who Keeps Feeder Roads Open?
In 2017 the World Bank approved a US$200 million credit for the Improved Rural Connectivity Project, noting that only 17% of Zambia’s rural population lived within 2 km of a good road. The project used output and performance-based road contracts (OPRC), in which contractors are paid for keeping roads at agreed service levels rather than for quantities of work.
The project’s closing date was 31 December 2025. Its results framework includes an indicator on whether government-funded road maintenance contracts exist for continued upkeep after the Bank-supported OPRC contracts end. That is the practical test now. Without a funded maintenance plan, gains on feeder roads can be lost within a few rainy seasons.
What a sound handover looks like
- 退出 OPRC 合同的每个路段列表及其移交时的状况
- A costed annual maintenance need for those sections, included in the Road Fund allocation
- A contracting model, performance-based or routine, with clear service levels
- Assigned responsibilities between the RDA and local road authorities
New Commitments: TRACER and Road Concessions
2024年2月,世界银行批准了一项2.7亿美元的赠款用于TRACER项目,该项目将修复达累斯萨拉姆走廊的塞伦杰至姆皮卡段,在纳孔德建设一站式边境哨所,并将该走廊改造成智能走廊。项目文件包括对区域走廊管理的支持以及政府实体中的机构能力建设。
The RDA has also reported 11 PPP concession agreements to upgrade and maintain over 1,002 km of roads, including the Lusaka–Ndola dual carriageway. An AfDB-supported pipeline study reviews Zambia’s PPP framework under the 2023 PPP Act and includes building the capacity of local practitioners to monitor and develop the pipeline. Concessions shift construction finance to private partners, but they create long-term monitoring duties and possible contingent liabilities that need clear reporting.
Lessons From Kenya’s Road Levy
Kenya offers a useful comparison. It raised its Road Maintenance Levy from Sh18 to Sh25 per litre in July 2024, and the Kenya Roads Board distributes it to national, urban, rural and county road authorities. Kenya Roads Board data shows a public network of 239,122 km in 2024 and an annual maintenance financing gap of Sh63 billion. In the year to June 2025, roads repaired fell 28% to 35,965 km after part of the levy was redirected. The lesson is that a dedicated fund helps, but only if its allocation rules are protected and transparent.
2027年实用议程
None of the steps below needs new legislation or large new budgets. Most are management routines that road agencies, road funds and the finance ministry can agree and start within a year. Together they address the main sources of loss identified in the audits: commitments made without matching cash, payments delayed in approval queues, variations approved without budget checks and securities that are not tracked.
| 行动 | Lead | What it prevents |
|---|---|---|
| Annual maintenance needs estimate from condition data, linked to Road Fund allocations | RDA, NRFA, local road authorities | 修复后道路的恶化 |
| Commitment check against medium-term budget ceilings before signing contracts | RDA, Ministry of Finance and National Planning | New arrears and interest |
| Certificate-to-payment tracking with target timelines | RDA, NRFA | Interest on late payment |
| Single register of advance payments, guarantees and expiry dates | RDA contracts unit | Unrecovered advances |
| Variation approval thresholds with budget confirmation | RDA 管理层与董事会 | Uncontrolled growth in contract values |
| 为每个前OPRC标段制定有资金支持的维护计划 | RDA, local road authorities | Loss of feeder road gains |
| Monitoring plan and fiscal risk reporting for each concession | RDA, PPP institutions, Ministry of Finance | Unplanned contingent liabilities |
| Audit recommendation tracker reported quarterly | All road sector bodies | Repeat findings |
Protecting the road from overloading
Maintenance financing is also about reducing damage in the first place. Heavy vehicles that exceed axle load limits shorten pavement life. Consistent weighbridge enforcement, accurate fine collection and data sharing between weighbridge operators and the road fund reduce the maintenance bill and support the case for protecting road fund revenue. Corridor projects that include new weighbridge facilities, as TRACER does at Mpika, are a good place to set these routines from the start.
Building skills across institutions
这些例行工作大多处于各机构之间:道路局、道路基金、地方道路机构和财政部。联合培训与共享工具(例如通用的合同登记册格式和商定的维护需求方法)有助于团队基于相同的数据开展工作,并减少每个交接环节发生的延误。
政府和项目负责人应当提出的关键问题
Do our contract commitments match the cash we expect?
Compare signed contract values and expected certificates with the medium-term budget for each year. Any gap will become arrears and interest.
哪些道路退出了捐助方资助的维护合同,现在由谁进行维护?
Every former OPRC section should have a named maintenance arrangement and budget line for 2027.
Can we see every advance payment and guarantee in one place?
包含到期日期的单一登记册可防止向过期担保和未收回预付款进行支付。
How are variations approved?
Set thresholds that require budget confirmation before a variation is signed, and record the reason for each one.
How will we monitor concessions for 20 years or more?
每个特许权都需要制定一项监控计划,涵盖绩效标准、通行费收入、维护义务、移交和财政承诺。
Are audit recommendations closed with evidence?
Track each finding with an owner, action, date and evidence, and report progress to the board and Parliament.
Risalat能提供哪些帮助
Risalat Consultants International partners with road agencies, road funds and finance ministries on maintenance planning, contract management and PPP oversight. Our Road Maintenance Financing & Contract Oversight Training in Nairobi works through these issues with Zambian and regional cases, and can be delivered in-house. Teams can also review their procurement systems with our free procurement maturity diagnostic.
常见问题
Who funds road maintenance in Zambia?
Mainly the Road Fund and tolling, managed by the National Road Fund Agency, with works delivered by the Road Development Agency and local road authorities.
What did the RDA special audit find?
About K9.89 billion owed to contractors and consultants at end-2022, K1.3 billion in interest for late payment and K2.13 billion added through variations on 14 contracts.
什么是OPRC合同?
An output and performance-based road contract pays the contractor for keeping a road at agreed service levels rather than for quantities of work; Zambia's World Bank-financed IRCP used this model.
How many road concessions does Zambia have?
The RDA has reported 11 PPP concession agreements to upgrade and maintain over 1,002 km of roads.
信息来源
- Zambia Monitor, special audit of the Road Development Agency 2017–2022
- 赞比亚监督员,RDA 专项审计(合同金额)
- Zambia Monitor, Auditor General's 2024 report
- Zambia Monitor, Auditor General's 2024 parastatal report
- Transparency International Zambia, simplified Auditor General report 2023
- UNDP, Zambia road safety investment case
- World Bank press release, IRCP approval, May 2017
- World Bank project page, IRCP (P159330)
- World Bank press release, TRACER, February 2024
- TRACER project information document (P180801)
- Zambia Monitor, RDA concession agreements
- Aninver, PPP project pipeline development in Zambia (AfDB)
- National Assembly of Zambia, committee report on Road Fund utilisation 2020–2024
- Business Daily, Kenya road maintenance levy
- Business Daily, Kenya road maintenance drops to six-year low