Contract Management Lessons: Audit Findings & Fixes
Short · 10 November 2026
Audit findings often highlight unauthorised contract variations and late settlement costs. Setting up live registers and clear approval maps solves these systemic issues before your next review. What slows down your contract approvals?
#Shorts #ContractManagement #Procurement #InternationalDevelopment
What this video covers
A short video for public institutions, development project teams and practitioners. It summarises the article CAG Report 2024/25 Tanzania: Contract Management Lessons for Projects, where the full analysis and sources are available.
- Unapproved changes are the largest exposure – variations and addenda worth TZS 66.08 billion and USD 2.28 million were approved and paid without the required authorisation.
- Late payment has a direct cost – contractor claims of TZS 81.79 billion were settled late and interest on late payments reached TZS 8.23 billion.
- Securities need active tracking – TZS 11.35 billion was paid while performance securities were absent or expired, and TZS 2.2 billion of advances lacked valid guarantees.
- TACTIC shows the local government angle – works of TZS 30.12 billion started before tender board approval and two councils executed TZS 7.12 billion of additional works without PO-RALG approval.
- Follow-up is the long-term test – only 36.7% of 38,181 earlier CAG recommendations had been fully implemented across all audits.