Public Procurement Rules 2026: Pakistan Agency Guide
Video · 7 November 2026
Federal procuring agencies in Pakistan must now align with the Public Procurement Rules 2026, which repeal the 2004 Rules. Learn the vital changes regarding e-PADS, direct contracting subcontracting caps, and revised grievance submission timelines. Which change presents the biggest operational challenge for your agency?
#PublicProcurement #Procurement #IMF
What this video covers
A video for public institutions, development project teams and practitioners. It summarises the article Public Procurement Rules 2026 in Pakistan: What Agencies Must Do Now, where the full analysis and sources are available.
- e-PADS is mandatory – Rule 8 requires all public procurement to be carried out through the E-Pak Acquisition and Disposal System, and PPRA has said this includes direct contracting.
- Accreditation has a deadline – Rule 10(2) gives officers in a Procurement Cell twelve months to obtain PPRA accreditation.
- Grievances move outside the agency – Rule 65 sets up committees completely outside the procuring agency, with a ten-day decision period and a 45-day appeal stage.
- Mis-procurement is defined – Rule 67(4) lists sixteen material deviations, from bypassing e-PADS to not using standard bidding documents.
- The evidence explains the change – PPRA's own 2025–26 review found violations in 80.58% of 103 sampled federal procurements.