Tajikistan's US$1.7 billion World Bank portfolio supports key infrastructure and services. Preparing early prevents implementation delays and cost overruns.

Risalat Consultants International
9 November 2026 · 7 min read
[Replaced] Delivering World Bank Projects in Tajikistan7 min read

Key takeaways

  • Tajikistan’s active World Bank portfolio comprises 28 projects totalling US$1.7 billion, with major financing across hydropower, public administration, water supply, sanitation, and education.
  • Implementation delays across energy, water, transport, and social facilities are typically rooted in issues that emerge before construction, including unverified site conditions, delayed permits, and resettlement.
  • Carrying out rigorous preparation, design reviews, market soundings, and institutional agreements prior to contract award protects project budgets and ensures assets can be operated sustainably.
  • Structured diagnostics, delivery frameworks, and role-based capacity development provide project implementation units with the operational tools required to maintain momentum.

Introduction

The active World Bank portfolio in Tajikistan represents a profound commitment to developing national infrastructure, human capital, and institutional capacity.⁣​‌​‌​​‌​​‌‌​‌‌​​​‌‌​​‌‌​​​‌‌​​​​​​‌​‌‌‌​​​‌‌​​​‌​‌‌‌‌​​​​‌‌​‌‌​​⁣ Totalling US$1.7 billion across 28 projects, these initiatives span critical national priorities. Delivering these complex investments on schedule and within budget requires rigorous operational discipline. International experience demonstrates that cost increases and project postponements are rarely caused by contractor performance alone; rather, they stem from systemic gaps during the project preparation phase. By identifying structural risks and establishing concrete operational measures before the first tender is launched, government ministries and project implementation units can safeguard public resources, accelerate disbursement, and achieve planned development outcomes.

What the money is for

The active portfolio channels resources into core productive sectors, public administration, and human development. Substantial resources are targeted at power generation and system reliability, including Renewable Energy Hydro (approximately US$494.7 million), Public Administration in Energy and Extractives (approximately US$315.7 million), and Energy Transmission and Distribution (approximately US$121.7 million). Foundational services also receive extensive support, including Water Supply (US$133 million), Sanitation (US$133 million), and Public Administration in Education (US$123 million). Significant investments also focus on disaster resilience, agricultural productivity, financial sector stability, early childhood development, and tax administration reform. Please refer to the table that follows for the detailed project listing.

ProjectApprovedWorld Bank financingSector
Sustainable Financing for Rogun Hydropower Project2024US$350.0m
Nurek Hydropower Rehabilitation Project Phase I2017US$225.7mRenewable Energy Hydro
Tajikistan Power Utility Financial Recovery2020US$134.0mPublic Administration – Energy and Extractives, Renewable Energy Hydro
Additional Financing to Power Utility Financial Recovery Project2022US$80.0mPublic Administration – Energy and Extractives, Energy Transmission and Distribution
Early Childhood Development to Build Tajikistan’s Human Capital Project2020US$73.0mPublic Administration – Education, Health Facilities and Construction
Additional Financing to Nurek Phase 22021US$65.0mRenewable Energy Hydro
Strengthening Resilience of the Agriculture Sector Project2021US$58.0mCrops, Agricultural markets, commercialization and agri-business
Rural Water Supply and Sanitation Project2019US$58.0mWater Supply, Sanitation

Energy and power

Energy and power infrastructure programmes represent the largest single share of development expenditure. However, complex energy initiatives frequently encounter bottlenecks during execution.

What goes wrong: Land access, wayleaves, and regulatory permits are often not secured before contracts commence, halting contractor mobilisation. Complex supply-and-install procurement processes frequently take far longer than planned due to market misalignment or delayed technical evaluations. Furthermore, newly constructed or rehabilitated assets sometimes prove difficult to operate sustainably because utility finances and tariff structures fail to cover ongoing operation and maintenance costs.

How to prevent it before the start: Complete a comprehensive readiness check of all required land parcels, wayleaves, permits, and engineering designs prior to initiating procurement, assigning a single accountable official and concrete deadlines to each item. Mitigate procurement delays by establishing realistic bidding schedules, conducting early market soundings to calibrate technical requirements, and appointing trained, dedicated bid evaluation committees. Finally, complete detailed operating cost and tariff analyses during the initial design stage, accompanied by formal asset management plans established from day one.

Water, sanitation and irrigation

Investments in clean water, sanitation networks, and agricultural irrigation are essential for public health and rural development, yet they face distinct operational vulnerabilities.

What goes wrong: Engineering designs prepared in offices often fail to reflect actual site conditions, forcing costly design variations and interruptions once civil works begin. In other instances, community water or irrigation schemes are successfully constructed but fall into disrepair because neither local user associations nor utility operators possess the resources or agreements to maintain them. In addition, unresolved environmental and social concerns can prompt community grievances that halt work on the ground.

How to prevent it before the start: Mandate thorough engineering design reviews and on-site physical verifications before issuing tender documents, backed by a formal change control procedure to govern any necessary modifications. Ensure operational sustainability by negotiating binding user or utility agreements, establishing realistic tariff collections, and setting out clear maintenance plans alongside civil works contracts. Ensure environmental and social instruments are fully prepared, adequately staffed, and operational before contractors mobilise, supported by an accessible, functioning grievance redress mechanism.

Transport and urban infrastructure

Linear infrastructure and municipal engineering projects demand extensive coordination across administrative jurisdictions and physical corridors.

What goes wrong: Uncompleted resettlement processes and delayed relocation of existing utility lines regularly prevent site handover, resulting in idle machinery claims from contractors. Inadequate oversight allows contract variations and contractor claims to accumulate, escalating overall costs. Additionally, weak or irregular site supervision leads to construction defects that compromise infrastructure lifespan.

How to prevent it before the start: Ensure that all resettlement action plans are fully executed, compensation is disbursed, and utility relocation agreements are finalised and funded prior to contract award. Establish robust contract management mechanisms by appointing named contract managers, instituting mandatory monthly progress reporting, and enforcing strict variation control procedures. Define supervision roles explicitly from the outset, requiring detailed quality management plans and independent technical verifications at defined construction milestones.

Health and nutrition

Social sector programmes that construct, renovate, or equip public facilities face challenges in synchronising physical inputs with human operations.

What goes wrong: Specialized medical supplies and clinical equipment frequently arrive on site before physical facilities are renovated or before staff have been trained to use them, causing storage damage and warranty expiration. Key development results become difficult to verify because monitoring systems lack reliable baseline data or practical collection mechanisms. Furthermore, completed facilities often struggle with service delivery due to lack of operational budgets and maintenance funding.

How to prevent it before the start: Develop an integrated, sequenced execution schedule that strictly synchronises civil works, equipment procurement, staff recruitment, and clinical training. Formulate an actionable results framework supported by clearly verifiable performance indicators and straightforward data collection routines. Engage central sector ministries during design to secure agreed budget lines and operational plans for ongoing facility upkeep and staffing.

A readiness check before the first contract

Prior to approving procurement packages or awarding initial contracts, project steering committees and management units should verify the following essential preconditions:

  • Site access and permits: Legal rights of way, land acquisition, site access agreements, and official building permits are fully secured and documented.
  • Verified engineering designs: Technical specifications and bill of quantities have undergone independent site verification and design audits to minimise variations.
  • Resettlement and compensation: Affected persons have received agreed compensation, and all physical relocation actions are completed ahead of handover.
  • Procurement readiness: Bidding documents, qualification criteria, and market assessments are fully completed, with trained evaluation committees officially designated.
  • Safeguards and grievance mechanisms: Environmental and social risk management plans are approved, implementation teams are in place, and a functional grievance redress process is active.
  • Operational sustainability: Agreements covering operation and maintenance arrangements, asset management responsibilities, and ongoing running costs are formally approved by the relevant authorities.
  • Supervision protocols: Named contract managers, engineering supervision consultants, and quality control systems are appointed with clear reporting mandates.

How Risalat can help

Addressing these implementation challenges requires access to proven tools, structured diagnostics, and practical operational approaches.⁣​‌​‌​​‌​​‌‌​‌‌​​​‌‌​​‌‌​​​‌‌​​​​​​‌​‌‌‌​​​‌‌​​​‌​‌‌‌‌​​​​‌‌​‌‌​​⁣ Project implementation teams and government authorities can leverage Risalat’s core service approaches to strengthen delivery:

Teams preparing and supervising operations can deploy practical analytical instruments, such as the Project Health Check to detect implementation bottlenecks early, and the Procurement Maturity Diagnostic to assess procurement system capabilities. Sector specialists can also draw upon structured Transformation blueprints to guide organizational change, and access the dedicated Workstation for project teams for practical project management workflows.

For targeted technical capability building aligned with the national portfolio, project staff can access specialized international programmes:

Source of project data: World Bank project records (projects.worldbank.org), read November 2026.

Share with your team

Know people who should read this? Become an Ambassador or write with Risalat.

Risalat Consultants International

Partners in project success since 2011, diagnostics, advisory support and applied learning for ministries, public agencies and project teams.

Need help putting this into practice?

Start with a free 10-minute diagnostic or talk to our experts.

Keep reading