Home › Free tools › Interface and Integration Risk Register
On multi-contractor programmes, many delays and claims start at the boundaries: one contractor waits for another's design data, access or connection. List each interface between two parties with its type, need date, status, likelihood, impact and owner. The register draws an interface matrix, rates and sorts the open interfaces, flags overdue and disputed items, shows which parties carry most exposure and gives the actions for your next interface meeting.
Need a verified result? Ask for an independent assessment by Risalat.
Upcoming programmes whose content matches the areas this tool measures. Your results show which fit your weakest areas.
Nothing here for your exact need? Ask for an in-house programme built around your gaps, or browse all programmes.
A point where the work, information or systems of two parties must fit together: physical (a connection), functional (one system relies on another), data, contractual, organisational, schedule or regulatory.
Usually the party that needs the input, with the owner's integration team as referee. Every interface needs one named owner.
Use Load to open a saved file, or copy rows in; the CSV button exports the register for Excel.
Sources checked: November 2026. We check the official sources every month.
A guidance tool, not a formal assessment, audit or legal opinion. Your contracts, the financier's policies and national law always take precedence.
We use essential cookies to run this website securely. With your permission we also use cookies for live chat, to understand how the site is used, and to measure our advertising. You can change your choice at any time from “Cookie settings” at the bottom of every page. Privacy and cookie policy
Most likely fit
Also worth a look
Less indicated by this result
Bid document issued
Bids opened
Evaluation and award decision
Contract signed
Bid validity
Bid document issued late in {n} package(s): preparing specifications, estimates and documents is a skill the team can build.
Bid document issued late in {n} package(s): check internal clearance and prior review timing as well.
Bid opening moved in {n} package(s): check how addenda, clarifications and deadline extensions are approved.
Evaluation and award decision late in {n} package(s): check committee appointment, report approval and no-objection steps.
Evaluation and award decision late in {n} package(s): evaluation reports may need practice with real cases.
Contract signature late in {n} package(s): check signature approvals, securities and other dependencies.
Long gaps between stages in {n} package(s): look for steps that wait on another unit.
{x} late in {n} packages: a recurring pattern often points to a practice gap.
Evaluation outlasted the bid validity in {n} package(s): confirm extensions and their effect on bids before any award.
More than half of the bid validity used in {n} package(s): plan extensions before the deadline.
Bid preparation period below the minimum in {n} package(s): an independent check before award is advisable.
Signature soon after the award decision in {n} package(s): confirm the standstill period was respected.
{x}: {n}%
Matched from the type of tool, as this result has no scores by area.
Nothing in this result points here.
No clear gap in this result. If problems persist, a short conversation helps locate them.
Overall result: {n}%
Lowest areas: {x}
{n} package(s) analysed, {x} behind plan
{x}: late in {n} package(s)
Bid validity and rule flags: {n}
Score: {x}
Result: {x}
Please complete the highlighted fields.
Connection problem. Please try again.
Sending…
A work email helps us confirm your institution and reply faster. A personal address is accepted.
See your result ↓
Back to questions ↑
A late stage or a low score shows where time or quality is being lost. It does not, on its own, show why. The cards below suggest which kind of support is most likely to fit, so a first conversation starts in the right place.
The team may need applied learning or coaching: practical work on its own files, so people can apply the rules and methods with confidence.
The institution may need to review its steps, approvals and dependencies: who signs, in what order, how long each step takes and what waits on what.
Dates, deadlines or validity periods are under pressure. A verified independent assessment is advisable before acting, so decisions rest on confirmed facts.
Screening aid, not a verified assessment. The matching uses your answers and a few fixed rules. Our specialists confirm the cause with you before recommending anything.